Representatives of the State Government and the City Hall of the Capital gathered on Wednesday (19) to discuss ways to accelerate the project to implement the new
The plan, which provides for the construction of buildings and remodeling in the region near Princess Isabel Square, is one of the main flags of management (Republicans).
The executive project, which provides for urban, traffic and infrastructure studies, should be ready by the end of the year. All these points need management authorization, which supports the work. It will be necessary, for example, the removal of 2,000 families living in the affected region.
Land cleaning is expected to take place by 2026 and the construction itself starts in 2027, with a period of completion of three years.
At the meeting, the state secretary of strategic projects, Guilherme Afif Domingos, suggested that a special committee will be created at the City Hall to optimize regulatory procedures, in a kind of “fast road”. Nunes management was analyzing the idea, but it nodded positively.