Train trips between Porto and Aveiro conditioned until the end of the year

by Andrea
0 comments
Train trips between Porto and Aveiro conditioned until the end of the year

Train trips between Porto and Aveiro conditioned until the end of the year

Night circulation and on weekends conditioned from Saturday, because of the construction of a lower passage at Gaia-Devesas station under the future Ruby of the Porto Ruby line.

The night rail circulation between Porto-Campanhã and Aveiro will be conditioned from Saturday and by the end of the year due to work in Ruby line construction from the port of Porto.

In a statement, Metro do Porto said that the construction of a lower passage at Gaia-Devesas station, under the Ruby line contract, implies conditioning in the rail circulation between Porto-Campanhã and Aveiro, especially at night and on weekends“In order to minimize impacts on passengers.”

“To ensure service and reduce the disorders caused by these conditioning”, The Porto Metro will ensure “Highway overflow to CP passengerswith stops with the following rail stations: Porto-SaSo Bento, Porto-Campanhã, General Torres, Gaia-Devesas, Coimbrões, Magdalene, Valadares, Francles, Miramar, Aguda, Farm, Espinho, Ovar and Aveiro (for long-haul services), ”he added.

The dates

Thus, on weekends from Saturday and until August 10, as well as September 20-28, there will be conditioning in the rail circulation from 23:50 to 7:50. Already on weekends from 17 to 31 August and from October 5 to December 2, the conditioning will take place between 22:00 and 10:00.

On business days, from August 11 to September 25 (includes the holiday from August 15) and from November 26 to December 12 (including the holidays from December 1st and 8th), the works will require the conditioning the rail circulation in that stretch between 23:00 and 05:00.

Ferreirinha ready only in 2027

The beginning of the construction of a lower passage at Gaia-Devesas station, which requires these conditioning, was articulated with Portugal’s infrastructure and CP-Comboios de Portugal, ensures the Porto Metro. A, with 6.4 kilometers and eight stations, includes one, the D. Antónia Ferreira Bridge, A, which will be exclusively reserved for the meter and pedestrian circulation and bicycles.

Em Gaiathe planned stations for the Rubi line are St. Ovid, Soares dos Reis, Devesas, Rotunda, Candal and Arrábida, and, in Porto, Campo Alegre and Casa da Música.

A contract must be completed by the end of 2026but a source of the port of Porto has already admitted to Lusa that the bridge should only be completed in 2027, being in question mainly finishes.

Initially, the project had a cost of 435 million euros. On April 16, the carrier’s president admitted that the total cost of the Ruby line, currently under construction between Casa da Música and Santo Ovidio, will rise by 50 million euros and the price can still increase.